Project Features:
- Two-Line Grout Curtain
- Fully documented, real-time, automated, grouting parameter monitoring and recording
- Remediation of earthen embankment dam and underlying rock foundation
- Pressure Grouting of soil and rock
- Used a suite of low to high mobility balanced, stable grouts
- Installed grout holes through sensitive impervious dam core
Background:
This project was performed for the Miami Conservancy District (MCD) under the direction of MWH Americas, Inc. (MWH) to mitigate seepage through the dam foundation and abutments. Lockington Dam was constructed approximately 90 years ago and was intended to control flooding and prevent a recurrence of the 1913 flood in Dayton, Ohio. Lockington Dam is of earthen construction, nearly 73 feet high and stretches a distance of 6,400 feet. It drains an area of roughly 255 square miles. It is one of 5 dams constructed by the district on the Miami River for flood control purposes.
Description of Work:
Pressure grouting was performed both in the rock foundation and in the overlying layers of glacial outwash and till. The hydraulic core material, which comprises most of the dam embankment, is extremely soft and prone to damage/deformation. Protection of the hydraulic core during drilling/grouting activities was a top priority on this project. To minimize the risk of damage to the core, Geo-Solutions chose Sonic Drilling methods to set casing through the hydraulic core. Sonic drilling uses high-frequency vibration transmitted from a specialty drill-head through the drill string, to fluidize soil particles that are in contact with the bit. This allows for efficient penetration of the soil without the use of water or drilling mud. Grout borings were installed by the following methods:
- Drill, by Sonic Drilling methods, through the soft hydraulic core material and grout a PVC casing in place to protect the core during the remainder of the drilling/grouting process.
- Advance steel casing, using casing advance methods, through the glacial outwash or till, to top of rock.
- Drill underlying foundation rock by rotary destructive-drilling methods.
Borings were installed vertically, up to 112-feet below ground surface, and were grouted in 10-foot (average) ascending stages. Grout passes through the header system prior to delivery to the target grout stage. Stages were isolated with a grout packer apparatus that consists of a single pneumatic packer attached to the bottom of an aluminum pipe string. Following rock grouting, the steel casing is extracted approximately 10-feet at a time and the exposed stages of glacial outwash or till are grouted under pressure by setting a grout packer in the steel casing.
Geo-Solutions performed real-time grout parameter monitoring during all grouting activities. Geo-Solutions’ custom grout monitors, manufactured by RST and Geonor, are staged at the grout header/manifold and contain a magnetic flow meter and electronic pressure transducer interfaced with an on-board data logger. Information from the data logger is transmitted, via R/F radio signal, from the header to a central computer system, which displays, in real-time, the pressure and flow readings in graphical format. The system also records and logs the pressure/flow readings in a file archive.
A suite of balanced, stable grouts were developed specifically for the project. Difficult or high-take stages were addressed by using higher unit-weight grout mixes containing Portland cement, bentonite, fly ash, and plasticizer.
Project Challenges:
Protection of the hydraulic core was paramount for this project. Constant adjustments were made in grouting procedures to ensure no damage was done to the sensitive embankment component. With as many as 6 drill rigs and two grouting crews, along with the required ancillary equipment, simultaneously operating on the dam on a daily basis, limited access and spatial constraints, due to dam crest width, created unique challenges with task coordination and productivity. Diligent planning was required to keep this project running smoothly.